I | Traction & Power Supply works: - i. Rigid Overhead Conductor System (ROCS), Auxiliary Substation (ASS) & 33 kV cabling works (Package - 11A)
- ii. Receiving Substation (RSS), 110 kV cabling & SCADA works(Package - 11B)
| - Contract Agreement signed with Consortium of Alstom Transport India Ltd and Alstom Transport S.A., France on 28.03.2018.
- Contract Agreement signed with Larsen & Toubro Limited on 06.04.2018.
- Physical Work Progress - Sariput Nagar RSS – 93% completed , Dharavi RSS- 85% completed , Science Museum RSS- 85% completed;
|
II | Tunnel Ventilation System (TVS) and Environmental Control Systems (ECS) (Package - 15) | - Tunnel Ventilation & Environmental Control System (TVE): Phase-1 (Aarey to BKC including): Contract Agreement signed with Shanghai Tunnel Engineering Co. Ltd (STEC), China on 14.03.2019.
- Tunnel Ventilation & Environmental Control System (TVE): Phase-2 Lot-1 (BKC excluding to Mumbai Central including): Contract Agreement signed with Blue Star Limited, India on 28.06.2019.
- Tunnel Ventilation & Environmental Control System (TVE): Phase-2 Lot-2 (Mumbai Central excluding to Cuffe Parade): Contract Agreement signed with M/s Voltas Limited, India on 20.09.2019.
|
III | Escalator works (Package - 16A ESTE1- Escalator) | - Escalators (EST): Lot-E1 (Aarey to Dadar, 13 Stations): Contract Agreement signed with Yuanda – Royal Consortium (Shenyang Yuanda Intellectual Industry Group Co. Ltd. China and Royal Infraconstru Ltd. India) on 28.03.2019.
- Escalators (EST): Lot-E2 (Siddhivinayak to Cuffe Parade, 14 Stations): Contract Agreement signed with Johnson Lifts Pvt Ltd India & M/s SJEC Corporation, China, Consortium on 28.03.2019
|
IV | Elevator/Lift works (Package-16B) | - JICA Pkg-16B: Lifts (LIF): Lot-L1 (Aarey to Dadar, 13 Stations): Contract Agreement signed with Joint venture of CRANEX and IFE (CRANEX Limited, India and IFE Elevator Co. Ltd. China) on 10.05.2019.
- JICA Pkg-16B: Lifts (LIF): Lot-L2 (Siddhivinayak to Cuffe Parade, 14 Stations): Contract Agreement signed with Yuanda-Royal Consortium (Shenyang Yuanda Intellectual Industry Group Co. Ltd. China and Royal Infraconstru Ltd. India) on15.03.2019.
|
V | Electrical & Mechanical (E & M) Works (7 packages) | - Awarded as part of Civil contracts
|
VI | Depot Pylon modification/shifting works | - Design Progress: 100%
- Material(Vendor) Finalized:99%
- Material Supplied:99%
- Site Installation: Civil -98%,Electrical- 82% Testing Progress:99% Overall Progress:92%
|
VII | Depot (E & M) works | - Contract Agreement signed with M/s Blue Star Limited, India on 30.11.2018.
|