Sr. No. | Nature of Work | Status |
---|---|---|
1 | Tunneling & Segment Production Progress | Wainganga-1 Drive-1 (From Pali ground to CSIA-T2) (UpLine) - Completed 1262rmt, Made Breakthrough on 24/09/2018. Drive-2 (From Pali Ground to SEEPZ) (UpLine)- Completed1689rmt, Made Breakthrough on 27/09/2019. Wainganga-2: Drive-1 (From Sariputnagar Ramp to SEEPZ) (DownLine)- Completed 568rmt, Made breakthrough on 26/12/2018 Drive-2 (From Pali Ground to SEEPZ) (DownLine)- Completed 1675rmt, Made Breakthrough at MIDC station on 12/12/2019 Wainganga-3: Drive-1 (From Pali Ground to CSIA-T2) (DownLine)- Completed 1313rmt, Made breakthrough on 13/02/2019 Drive-2 (From Sariputnagar Ramp to SEEPZ) (UpLine)- Completed 572rmt, Made breakthrough on 13/08/2019 Segment Production PRogress: 100% of total completed. |
2 | Excavation | Station Box area: Marol Naka: 100% completed MIDC: 100% completed SEEPZ: 100% completed Ramp: 100% completed (including Cut & Cover and shaft area) |
3 | Base Slab Progress | Marol Naka: 100% Completed MIDC: 100% Completed SEEPZ: 100% Completed Concourse Slab Marol Naka: 100% Completed MIDC: 100% Completed SEEPZ: 100% Completed Roof Slab Marol Naka: 100% Completed MIDC: 100% completed SEEPZ: 100% completed Mezzanine slab Marol Naka: 100% Completed |
4 | Secant Piling Progress | Marol Naka: 100% completed MIDC: 100% completed SEEPZ: 100% completed Ramp: 100% completed (including Cut & Cover and shaft area) |
5 | Rehabilitation & Resettlement | _______ |
6 | Building condition Survey | Completed. |
7 | Tree Cutting/transplantation | Marol: Tree Cutting: 7/9, Tree Transplantation: 42/50 MIDC: Tree Cutting: 9/11, Tree Transplantation: 90/130 SEEPZ: Tree Cutting: 9/12, Tree Transplantation: 84/115
|
8 | Traffic Diversion | Marol Naka: 100% Completed MIDC: 100% Completed. SEEPZ: 100% Completed. |
9 | Geo-technical investigation | 100% Completed |
10 | Barricading | All the acquired area 100% barricaded. |
11 | Civil station progress | a) Marol Naka -91.5% b) MIDC -94.3% c) Seepz-94.1% |