Sr. No. | Package Name | Package status |
---|---|---|
1 | Procurement of Rolling Stock
|
|
2 | Procurement of Depot Machine & Plant
|
|
Sr. No. | Package Name | Package status |
---|---|---|
1 | Procurement of Rolling Stock
|
|
2 | Procurement of Depot Machine & Plant
|
|
Sr. No | Nature of Work | Status |
---|---|---|
1 | Barricading | 100 % completed. In progress with the construction works. |
2 | Rehabilitation & Resettlement | Completed. |
3 | Traffic Diversion | Completed. |
4 | Geo-technical investigation | 100% completed. |
5 | Building condition Survey | Completed. |
6 | Tunneling Progress | Science Museum- Worli (Tansa-1) – 1382/ 1382 rings has been erected. (100 % completed) Science Museum- Worli (Tansa-2) – 1372 / 1372 rings has been erected. (100 % completed)
Science Museum-Mumbai Central (Tansa-2) – 1182 / 1308 rings has been erected. (90.36 % Completed) Science Museum-Mumbai Central (Tansa-1) – 792 / 1303 rings has been erected. (60.78 % Completed) |
7 | Segment Production Progress | 100 % of the total scope of permanent rings has been completed. |
8 | Secant Piling Progress | Station Box Area:
Mumbai Central – 100 % completed Mahalaxmi – 100 % completed Science Museum – 100 % completed Acharya Atre Chowk –100 % completed Worli – 100 % completed |
9 | Traffic Decking & King Posts |
Mumbai Central –100 % has been completed. Mahalaxmi – 100 % has been completed. Acharya Atre Chowk- 100 % has been completed. Worli – 100 % has been completed.
|
10 | Excavation (Station Box) | Mumbai Central: 2,14,164 / 2,14,164 cu.m ( 100% ) has been completed.
Mahalaxmi: 1,66,229 / 1,66,229 cu.m ( 100%) has been completed.
Science Museum : 2,11,816 / 2,11,816 cu.m ( 100 %) has been completed.
Acharya Atre Chowk: 1,87,375 / 1,87,375 cu.m ( 100 % ) has been completed.
Worli: 1,77,370 / 1,77,370 cu.m ( 100% ) has been completed.
|
11 | Base Slab Progress | Mumbai Central: 100 % of the total scope has been completed.
Mahalaxmi: 100% of the total scope has been completed.
Science museum: 100 % of the total scope has been completed.
Acharya Atre Chowk: 100 % of the total scope has been completed.
Worli: 100 % of the total scope has been completed.
|
12 | Concourse Slab Progress | Mumbai Central: 100 % of the total scope has been completed.
Mahalaxmi: 100 % of the total scope has been completed.
Science museum: 100 % of the total scope has been completed.
Acharya Atre Chowk: 87 % of the total scope has been completed.
Worli: 98 % of the total scope has been completed.
|
13 | Roof Slab Progress |
Mumbai Central: 100 % of the total scope has been completed.
Mahalaxmi: 100 % of the total scope has been completed.
Science museum: 100 % of the total scope has been completed.
Acharya Atre Chowk: 58 % of the total scope has been completed.
Worli: 97 % of the total scope has been completed.
|
14 | Platform Slab Progress | Mumbai Central: 68 % of the total scope has been completed.
Mahalaxmi: 20 % of the total scope has been completed.
Science museum: 69 % of the total scope has been completed.
Acharya Atre Chowk: 39 % of the total scope has been completed.
Worli: 57 % of the total scope has been completed.
|
Sr. No. | Nature of Work | Status |
---|---|---|
1 | Tunneling & Segment Production Progress | Wainganga-1 Drive-1 (From Pali ground to CSIA-T2) (UpLine) - Completed 1262rmt, Made Breakthrough on 24/09/2018. Drive-2 (From Pali Ground to SEEPZ) (UpLine)- Completed1689rmt, Made Breakthrough on 27/09/2019. Wainganga-2: Drive-1 (From Sariputnagar Ramp to SEEPZ) (DownLine)- Completed 568rmt, Made breakthrough on 26/12/2018 Drive-2 (From Pali Ground to SEEPZ) (DownLine)- Completed 1675rmt, Made Breakthrough at MIDC station on 12/12/2019 Wainganga-3: Drive-1 (From Pali Ground to CSIA-T2) (DownLine)- Completed 1313rmt, Made breakthrough on 13/02/2019 Drive-2 (From Sariputnagar Ramp to SEEPZ) (UpLine)- Completed 572rmt, Made breakthrough on 13/08/2019 Segment Production PRogress: 100% of total completed. |
2 | Excavation | Station Box area: Marol Naka: 100% completed MIDC: 100% completed SEEPZ: 100% completed Ramp: 100% completed (including Cut & Cover and shaft area) |
3 | Base Slab Progress | Marol Naka: 100% Completed MIDC: 100% Completed SEEPZ: 100% Completed Concourse Slab Marol Naka: 100% Completed MIDC: 100% Completed SEEPZ: 100% Completed Roof Slab Marol Naka: 100% Completed MIDC: 100% completed SEEPZ: 100% completed Mezzanine slab Marol Naka: 100% Completed |
4 | Secant Piling Progress | Marol Naka: 100% completed MIDC: 100% completed SEEPZ: 100% completed Ramp: 100% completed (including Cut & Cover and shaft area) |
5 | Rehabilitation & Resettlement | _______ |
6 | Building condition Survey | Completed. |
7 | Tree Cutting/transplantation | Marol: Tree Cutting: 7/9, Tree Transplantation: 42/50 MIDC: Tree Cutting: 9/11, Tree Transplantation: 90/130 SEEPZ: Tree Cutting: 9/12, Tree Transplantation: 84/115
|
8 | Traffic Diversion | Marol Naka: 100% Completed MIDC: 100% Completed. SEEPZ: 100% Completed. |
9 | Geo-technical investigation | 100% Completed |
10 | Barricading | All the acquired area 100% barricaded. |
11 | Civil station progress | a) Marol Naka -91.5% b) MIDC -94.3% c) Seepz-94.1% |
Sr. No | Nature of Work | Status |
---|---|---|
1 | Barricading | Handed over areas barricaded |
2 | Rehabilitation & Resettlement | Vidhan Bhavan Station: Alternate eatery (Kutumbsakhi) has been occupied at new location. Hutatma Chowk: Container placed at alternate location for Police Chowky. Electricity & water connection and signing of MoU awaited for shifting. |
3 | Traffic Diversion & Decking | Phase-1 Traffic Diversions implemented at all station locations Cuffe Parade- Deck at service lane open to traffic Vidhan Bhavan- Both decks at Free Press Journal Road open to traffic Churchgate- Straight Deck and cross deck open to traffic. Hutatma Chowk- Straight Deck open to traffic Mid Shaft- Approval Awaited |
4 | Geo-technical investigation | Completed for all stations and alignment |
5 | Tree Cutting/transplantation | Cuffe Parade Station - Scope: (To be transplanted/to be cut)= 123 / 196 Completed: ( transplanted/ cut ) = 120 / 190 Vidhan Bhavan Station - Scope: (To be transplanted/to be cut)= 94 / 116 Completed: ( transplanted/ cut ) = 67/92 (All cutting/ transplantation completed as 23 trees are being saved) Church Gate Station Scope: (To be transplanted/to be cut)= 47 /51 Completed: ( transplanted/ cut ) = 40 / 38 (All cutting/ transplantation completed as 51 trees are being saved) Hutatma Chowk Station Scope: (To be transplanted/to be cut)= 76 / 45 Completed: ( transplanted/ cut ) = 44 / 43 (All cutting/ transplantation completed as 35 are being saved) Mid Shaft Scope: (To be transplanted/to be cut)= 03 / 05 Completed: ( Transplanted/ cut ) = 02/ 03 |
6 | Building condition Survey | 100% completed |
7 | Tunneling Progress | TBM Ring Building(rmtr): TBM1: Total completed: 2,926.5 Scope: 2,926.5(4 Breakthrough Over) TBM2: Total completed: 2,939.3 Scope: 2,939.3 (4 Breakthrough Over) First Stage Concrete: TBM1: Total completed:2,910.4 Scope: 2,910.4(Started on 06/01/21 in SCP to SVB Upline, started on 05/02/21 in SVB to SCG Upline, started on 19/08/21 in SCG to SHC Upline, Started on 06/11/21 in SHC to CST Upline)
TBM2: Total completed: 2,919 Scope: 2939.3 (Started on 02/12/20 at SVB to SCG Downline; Started on 27/03/21 in SCP to SVB Downline, Started on 30/07/21 in SCG to SHC Downline)
NATM 1: Total completed: 199.12 Scope: 199.12 (Started on 03/04/21 at SCP NATM 1 Upline) NATM 2: Total completed: 200.2 Scope: 200.2 (Started on 30/04/21 at SCP NATM 2 Downline) |
8 | Segment Production Progress | 100% Complete (4,166 nos) |
9 | Secant Piling Progress | Cuffe Parade Station - Total completed -1,371; Scope –1,371(Only Station Box); Entry Exit: 347 out of 347 completed; Vent Shaft: 26 out of 26 completed. Vidhan Bhavan Station - Total completed -1,897; Scope – 1,897 (Station Box Piling completed); Church Gate Station - Total completed -1,406; Scope – 1,406 Hutatma Chowk Station - Total completed – 1,796; Scope – 1,796; Utility Gallery: 97 out of 160 completed. Mid Shaft - Total completed – 172; Scope – 172 (Secant Piles) Total completed – 50; Scope – 50 (ISMB Soldier Piles) |
10 | Excavation | Cuffe Parade Station: 305265 cum. out of 3,06,750 cum. Vidhan Bhavan Station: 217189.01 cum. out of 2,17,474 cum.
Churchgate Station: 207831.37 cum. out of 2,13,592 cum.
Hutatma Chowk Station: 178271.84 cum. out of 1,81,998 cum.
Mid Shaft: 13,724 cum. out of 13,724 cum. |
11 | Permanent Works | Permanent Base Slab:
Concourse Slab:
Mezzanine/ Other Slab:
Roof Slab:
Platform Slab:
|
12 | NATM Tunnel (Heading) | Upline: Total Completed: 199.12m Scope: 199.12m Downline: Total Completed: 200.20m Scope: 200.20m SHC NATM PF: Total Completed: 257.50m Scope: 257.5m |
13 | NATM Tunnel (Benching) | Upline: Total Completed: 199.12m Scope: 199.12m Downline: Total Completed: 200.20m Scope: 200.20m SHC NATM PF: Total Completed: 257.5m Scope: 257.5m |
14 | NATM Tunnel (Secondary Lining) | Upline Invert: 199.12m completed out of 199.12m Upline Overt: 199.12m completed out of 199.12m Downline Invert: 200.0m completed out of 200.20m Downline Overt: 200.2m completed out of 200.20m SHC NATM PF Invert: Total Completed: 258m Scope: 257.50m SHC NATM PF Overt: Total Completed: 73m Scope: 257.50m |
Sr. No. | Nature of Work | Status |
---|---|---|
1 | Tunneling & Segment Production Progress | CSIA T2 Metro Station |
Tunnel CSIA T2 to Sahar Road Station (Downline): | ||
Permanat Ring: Total Progress - 491, Scope - 491 | ||
Completed | ||
Permanat Ring: Total Progress - 491, Scope - 491 | ||
Completed | ||
Tunnel MVS to CSIA T1 (Upline): | ||
Permanat Ring: Total Progress - 910, Scope - 910 | ||
Completed | ||
Tunnel MVS to CSIA T1 (Downline): | ||
Permanat Ring: Total Progress - 892, Scope - 892 | ||
Completed | ||
Sahar Road Station to CSMIA | ||
Domestic Airport Station (Downline) | ||
Permanat Ring: Total Progress - 1080, Scope - 1080 | ||
Segment Production Progress: | ||
Permanent Rings: Total progress - 4949, Scope - 4949 | ||
2 | Excavation | CSIA T1 Metro station |
Total progress - 268971 Cum. Scope - 268471 Cum. (Work in progress) | ||
Sahar road Station | ||
Total progress - 322478 Cum. Scope - 322478 Cum. (Completed) | ||
CSIA T2 Metro Station | ||
Total progress - 468642 Cum. Scope - 468642 Cum. (Completed) | ||
3 | Base Slab Progress | CSIA T1 Metro station: |
Base Slab Completed. | ||
Concourse Slab: Total progress - 196 m. Scope - 198 m. (Work in progress) | ||
Concourse to Roof Slab: Total progress - 370 m. Scope - 390 m. (Work in progress) | ||
Roof Slab: Total progress - 196 m. Scope - 198 m. (Work in progress) | ||
CSIA T2 Metro Station: | ||
Base Slab Completed. | ||
Concourse Slab: Total progress - 311 m. Scope - 314 m. (Work in progress) | ||
Concourse to Roof Wall: Total progress - 499 m. Scope - 541 m. (Work in progress) | ||
Roof Slab: Total progress - 311 Cum. Scope - 314 m. (Work in progress) | ||
Sahar Road Metro station: | ||
Base Slab Completed. | ||
Concourse Slab: Total progress - 220 m. Scope - 220 m. (Completed) | ||
Concourse to Roof Slab: Total progress - 328 m. Scope - 328 m. (Completed) | ||
Roof Slab: Total progress - 220 Cum. Scope - 220 m. (Completed) | ||
4 | Secant Piling Progress | CSIA T1 Metro station |
Secant piles: Total progress - 808, Scope - 808 | ||
Micro piles: Total progress - 154, Scope - 154 | ||
Sahar road Station | ||
Secant piles: Total progress - 1121, Scope - 1121 | ||
Subway secant piles: Total progress - 67, Scope - 67 | ||
CSIA T2 Metro Station | ||
Secant piles: Total progress - 1298, Scope - 1298 | ||
5 | Rehabilitation & Resettlement | ______ |
6 | Building condition Survey | Pre-condition survey this week - 0 |
Total Progress - 60 | ||
Scope - 60 | ||
7 | Tree Cutting/transplantation | CSIA T1 - Total progress - 3 , Scope - 3 , Completed |
Transplantation - 60 out of 112 | ||
Sahar Rorad - Total progress - 4 , Scope - 4 , Completed | ||
Transplantation - 177 out of 226 | ||
CSIA T2 - Total progress - 0 , Scope - 0 , Completed | ||
Transplantation - 4 out of 4 completed | ||
8 | Traffic Diversion | SAHAR ROAD STATION: |
Road diversion: Stage-1 Completed | ||
Subway completed | ||
Sahar Shadow Road: | ||
Commissioned on 27th July 2018. | ||
Caping beam & Flood Wall: Completed | ||
CSIA T2 Metro Station: | ||
Internal Road: Completed. | ||
Ancillary Works for TBM Launching: Completed | ||
9 | Geo-technical investigation | SAHAR Road Metro station |
Completed | ||
Sahar Road to International Station | ||
CSIA T1 Metro Station | ||
Completed | ||
CSIA T2 Metro Station | ||
Completed | ||
10 | Barricading | SAHAR Road Metro station |
All construction Works is going on within | ||
secured barricading area . | ||
CSIA T1 Metro station | ||
Completed | ||
CSIA T2 Metro station | ||
Completed | ||
Construction Depot JVLR (GI Sheets) | ||
Completed |
1. ITO Junction-BKC | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | Scope(No.) | This Week | Total Progress | %Completion | Remarks | ||||||
Decking Plate Erection-Phase 1 | 550 | - | 550 | 100% | Completed | ||||||
Decking Plate Erection-Phase 1 | 550 | - | 550 | 100% | Completed |
2. Utility Diversion | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
2.1. Dharavi | |||||||||||
Utility Type | Total Scope (Rmt) | This Week | Total Progress | % Completion | Remarks | ||||||
450 mm Dia Water Line (Building side) | 332 | - | 332 | 100% | Completed | ||||||
SWD - 2200 X 2200 East | 155 | - | 155 | 100% | Completed | ||||||
900 mm Dia Water Line | 300 | - | 300 | 100% | Completed | ||||||
1200 mm SWD Building site | 300 | - | 300 | 100% | Completed | ||||||
5.2. BKC | |||||||||||
900 mm Dia SWD – TATA Footpath | 165 | - | 165 | 100% | Completed | ||||||
600 mm Dia SWD – IT Junction | 210 | - | 210 | 100% | Completed | ||||||
SWD Line- 2m X 2m | 48 | - | 48 | 100% | Completed | ||||||
450mm Dia SWD- N. Shaft | 165 | - | 165 | 100% | Completed | ||||||
5.3. Vidyanagari | |||||||||||
300 mm Dia Sewer Line (N. Shaft) | 325 | - | 325 | 100% | Completed | ||||||
SWD & Culvert | 205 | - | 205 | 100% | Completed | ||||||
600 mm Dia Pipeline(Phase 1) | 232 | - | 232 | 100% | Completed | ||||||
1200 mm Dia Pipeline | 245 | - | 245 | 100% | Completed | ||||||
5.4. Santacruz | |||||||||||
600 mm Dia Sewer Line | 150 | - | 150 | 100% | Completed | ||||||
SWD Below flyover | 360 | - | 360 | 100% | Completed | ||||||
300mm Dia Sewer line | 280 | - | 280 | 100% | Completed | ||||||
5.5. MVS | |||||||||||
1200 mm Water Line Diversion | 45 | - | 45 | 100% | Completed |
3. PILING | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
3.1. Dharavi | |||||||||||
Location | Total Scope (Nos) | This Week | Total Progress | % Completion | Remarks | ||||||
North Retrieval & Ancillary | 307 | - | 307 | 100% | Completed | ||||||
Station Box | 779 | - | 779 | 100% | Completed | ||||||
Decking Piles-King Post (Interconnection) | 52 | - | 52 | 100% | Completed | ||||||
3.2. BKC | |||||||||||
Location | Total Scope (Nos) | This Week | Total Progress | % Completion | Remarks | ||||||
North Launching shaft | 180 | - | 180 | 100% | Completed | ||||||
Station Box | 1155 | - | 1155 | 100% | Completed | ||||||
South Launching | 185 | - | 185 | 100% | Completed | ||||||
Decking Piles | 6 | - | 6 | 100% | Completed | ||||||
Entry/Exit-15-19-East(E10) | 76 | - | 76 | 100% | Completed | ||||||
Entry/Exit-15-19-East(E11) | 121 | - | 121 | 100% | Completed | ||||||
Entry/Exit-15-19-East(E05) | 292 | - | 229 | 74% | Ongoing | ||||||
Entry/Exit-15-19-East(E02) | 176 | - | 176 | 100% | Completed | ||||||
Entry/Exit-38-40-East(E07) | 220 | - | 162 | 13% | Ongoing | ||||||
Entry/Exit-11-13-East(E04) | 93 | 6 | 26 | 28% | Ongoing | ||||||
3.3. Vidyanagri | |||||||||||
Location | Total Scope (Nos) | This Week | Total Progress | % Completion | Remarks | ||||||
North Launching shaft | 176 | - | 176 | 100% | Completed | ||||||
Station Box | 894 | - | 894 | 100% | Completed | ||||||
3.4. Santacruz | |||||||||||
Location | Total Scope (Nos) | This Week | Total Progress | % Completion | Remarks | ||||||
Secant pile | 585 | - | 585 | 100% | Completed | ||||||
Micro pile(station box) | 2182 | - | 2182 | 100% | Completed | ||||||
Secant pile-(ent/ext)-South Entry Exit | 163 | - | 163 | 100% | Completed | ||||||
Secant pile-(ent/ext)-North Entry Exit | 112 | - | 112 | 100% | Completed | ||||||
Entry - Exit (Micro Piles) Gr 07 (South West Entry Exit) | 465 | - | 465 | 100% | Completed | ||||||
Entry - Exit (Micro Piles) Gr 17 (North West Entry Exit) | 469 | - | 469 | 100% | Completed | ||||||
Entry - Exit (Secant Piles) Gr 07 (SW Entry Exit) | 252 | - | 252 | 100% | Completed | ||||||
Entry - Exit (Micro Piles) Gr 17 (N-W Entry Exit) | 333 | - | 333 | 100% | Completed | ||||||
3.5. MVS | |||||||||||
Secant Pile | 184 | - | 184 | 100% | Completed |
4. Capping Beam | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
4.1. Dharavi | |||||||||||
Location | Total Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Station Box | 717 | - | 717 | 100% | Completed | ||||||
4.2. BKC | |||||||||||
North Launching Shaft | 133 | - | 133 | 100% | Completed | ||||||
Station Box | 860 | - | 860 | 100% | Completed | ||||||
South Launching Shaft | 109 | - | 109 | 100% | Completed | ||||||
4.3. Vidyanagri | |||||||||||
North Shaft | 110 | - | 110 | 100% | Completed | ||||||
Station Box | 680 | - | 680 | 100% | Completed | ||||||
4.4. Santacruz & MVS | |||||||||||
Station Box-Santacruz | 560 | - | 560 | 100% | Completed | ||||||
North E&E-Santacruz | 60 | - | 60 | 100% | Completed | ||||||
Station Box-MVS | 110 | - | 110 | 100% | Completed |
5. Excavation | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Station Box (Dharavi) | 179000 | - | 1,79,000 | 100% | Completed | ||||||
Station Box (BKC) | 377624 | - | 3,77,624 | 100% | Completed | ||||||
Station Box (Vidyanagri) | 161118 | - | 1,61,118 | 100% | Completed | ||||||
Santacruz (Station box) | 104500 | - | 1,04,500 | 100% | Completed | ||||||
Entry Exit (BKC)(EE02) | 4736 | - | 3290 | 68% | Ongoing | ||||||
Entry Exit-SSC (NWEE &SWEE) | 23578 | 110 | 19700 | 83% | Ongoing |
6. Permanent Works-Dharavi | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | UOM | Scope | This Week | Total Progress | % Comp | Remarks | |||||
Base Slab | Rmt | 250 M | - | 250 M | 100% | Completed | |||||
Concourse Slab | Rmt | 250 M | - | 250 M | 100% | Completed | |||||
Roof Slab | Rmt | 250 M | - | 250 M | 100% | Completed | |||||
Platform Slab | Rmt | 250 M | - | 250 M | 100% | Completed | |||||
Pop up Walls | Rmt | 790 M | 507 M | 57.5% | Ongoing | ||||||
Pop up Slab | Nos | 10 | 6 | 35% | Ongoing | ||||||
EE Slabs | Nos | 8 | 6 | 63% | Ongoing | ||||||
Ancillary Slabs | Nos | 6 | 5.5 | 64% | Ongoing | ||||||
Backfilling | Cum | 38961 | 22521 | 57% | Ongoing | ||||||
Blockwork | Cum | 1337 | 11 | 1021 | 76% | Ongoing |
7. Permanent Works-BKC | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | UOM | Scope | This Week | Total Progress | % Comp | Remarks | |||||
Base Slab | Rmt | 474 M | - | 474 M | 100% | Completed | |||||
Concourse Slab | Rmt | 474 M | - | 463 MM | 95% | Ongoing | |||||
Roof Slab | Rmt | 474 M | - | 445 M | 94% | Ongoing | |||||
Platform Slab | Rmt | 674 M | - | 655 M | 97% | Ongoing | |||||
Pop up Walls | Rmt | 782 M | 439 M | 56% | Ongoing | ||||||
Pop up Slab | Nos | 11 | 4 | 36% | Ongoing | ||||||
EE Slabs | Nos | 32 | 3.5 | 63% | Ongoing | ||||||
Ancillary Slabs | Nos | 4 | 2 | 50% | Ongoing | ||||||
Backfilling | Cum | 97,135 | 26,100 | 26% | Ongoing | ||||||
Blockwork | Cum | 2,458 | 12 | 2,265 | 86% | Ongoing |
8. Permanent Works-Vidyanagari | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | UOM | Scope | This Week | Total Progress | % Comp | Remarks | |||||
Base Slab | Rmt | 250 M | 6 | 242 M | 98% | Ongoing | |||||
Concourse Slab | Rmt | 250 M | 238 M | 95% | Ongoing | ||||||
Roof Slab | Rmt | 250 M | 232 M | 93% | Ongoing | ||||||
Platform Slab | Rmt | 250 M | 227 M | 91% | Ongoing | ||||||
Pop up Walls | Rmt | 544 M | 507M | 84% | Ongoing | ||||||
Pop up Slab | Nos | 8 | 7 | 87% | Ongoing | ||||||
EE Slabs | Nos | 4 | 4 | 100% | Completed | ||||||
Ancillary Slabs | Nos | 6 | 5 | 91% | Ongoing | ||||||
Backfilling | Cum | 39848 | 18643 | 44% | Ongoing | ||||||
Blockwork | Cum | 1676 | 4 | 1095 | 64% | Ongoing |
9. Permanent Works-Santacruz | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | UOM | Scope | This Week | Total Progress | % Comp | Remarks | |||||
Base Slab | Rmt | 252 M | 252 M | 100% | Completed | ||||||
Concourse Slab | Rmt | 252 M | 252 M | 100% | Ongoing | ||||||
Roof Slab | Rmt | 252 M | - | 252 M | 100% | Ongoing | |||||
Platform Slab | Rmt | 252 M | - | 242 M | 96% | Ongoing | |||||
Plant Room Base Slab | Rmt | 91 M | 91 | 100% | Completed | ||||||
Pop up Walls | Rmt | 773 M | 533M | 72% | Ongoing | ||||||
Pop up Slab | Nos | 9 | 6 | 66% | Ongoing | ||||||
Shafts | Nos | 9 | 3 | 22% | Ongoing | ||||||
Backfilling | Cum | 27928 | 10464 | 37% | Ongoing | ||||||
Blockwork | Cum | 1589 | 5 | 901 | 64% | Ongoing |
10. NATM: BKC South | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Excavation-Heading | 153 | - | 153 | 100% | Completed | ||||||
Excavation-Benching | 153 | - | 153 | 100% | Completed | ||||||
Concreting-Invert | 153 | - | 153 | 100% | Completed | ||||||
Concreting-Overt | 153 | - | 153 | 100% | Completed | ||||||
Concreting-Invert | 8.3 | - | Ongoing | ||||||||
Concreting-Overt | 8.3 | - |
11. NATM: BKC North | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Excavation-Heading | 153 | 153 | 100% | Completed | |||||||
Excavation-Benching | 153 | 153 | 100% | Completed | |||||||
Concreting-Invert | 153 | - | 153 | 100% | Completed | ||||||
Concreting-Overt | 153 | - | 153 | 100% | Completed |
12. NATM: SANTACRUZ (PLATFORM TUNNEL) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Excavation-Heading | 272 | 272 | 100% | Completed | |||||||
Excavation-Benching | 272 | 272 | 100% | Completed | |||||||
Concreting-Invert | 272 | - | 272 | 100% | Completed | ||||||
Concreting-Overt | 272 | - | 272 | 100% | Completed |
13. NATM: CROSS PASSAGES – (SBA to MVS) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
CP – 507 | 1 | - | 1 | 100% | Completed | ||||||
CP – 508 | 1 | - | 1 | 100% | Completed | ||||||
CP – 509 | 1 | - | 1 | 100% | Completed | ||||||
CP – 510 | 1 | - | 1 | 100% | Completed | ||||||
CP – 511 | 1 | - | 1 | 100% | Completed | ||||||
CP – 512 | 1 | - | 1 | 100% | Completed | ||||||
NATM CP-01 | 1 | - | 1 | 100% | Completed | ||||||
NATM CP-02 | 1 | - | 1 | 100% | Completed | ||||||
NATM CP-03 | 1 | - | 1 | 100% | Completed |
14. NATM: CROSS PASSAGES – (SBA to SDH) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
CP – 501 | 1 | 1 | 100% | Completed | |||||||
CP – 502 | 1 | 1 | 100% | Completed | |||||||
CP – 503 | 1 | 1 | 100% | Completed | |||||||
CP – 504 | 1 | 1 | 100% | Completed | |||||||
CP – 505 | 1 | 1 | 100% | Completed | |||||||
CP – 506 | 1 | 1 | 100% | Completed |
15. NATM: CP – (SSC) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
A1 | 1 | 1 | 100% | Completed | |||||||
B1 | 1 | 1 | 100% | Completed | |||||||
C1 | 1 | 1 | 100% | Completed | |||||||
A2 | 1 | 1 | 100% | Completed | |||||||
B2 | 1 | 1 | 100% | Completed | |||||||
C2 | 1 | 1 | 100% | Completed | |||||||
A4 | 1 | 1 | 100% | Completed | |||||||
A5 | 1 | 1 | 100% | Completed | |||||||
A6 | 1 | 1 | 100% | Completed |
16. NATM: SANTACRUZ (Ventilation Tunnel) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Excavation-Heading | 23 | 23 | 100% | Completed | |||||||
Excavation-Benching | 23 | 23 | 100% | Completed | |||||||
Concreting-Invert | 23 | - | 23 | 100% | Completed | ||||||
Concreting-Overt | 23 | - | 23 | 100% | Completed |
Sr. No. | Nature of Work | Project Status |
1 | Tunneling Works |
|
2 | Station Works |
Entrances
Base Slab: 553 Sqm/553 Sqm (100% Completed) Intermediate Slab: 628 Sqm/628 Sqm (100% Completed) Roof Slab: 740 Sqm/740 Sqm (100% Completed)
Base Slab: 639 Sqm/639 Sqm (100% Completed) Intermediate Slab: 662 Sqm/662 Sqm (100% Completed) Roof Slab: 399 Sqm/399 Sqm (100% Completed)
Base Slab: 375 Sqm/375 Sqm (100% Completed) Intermediate Slab: 238 Sqm/238 Sqm (100% Completed) Roof Slab: 175 Sqm/175 Sqm (100% Completed)
Base Slab: 272 Sqm/272 Sqm (100% Completed) Roof Slab: 206Sqm/206 Sqm (100% Completed)
Base Slab: 143 Sqm/143 Sqm (100% Completed) Roof Slab: 212 Sqm/212 Sqm (100% Completed)
Base Slab: 65 Sqm/86.4 Sqm (75% Completed) Roof Slab:61Sqm/61 Sqm (100% Completed)
Entrances
Base Slab: 80 Sqm/80 Sqm (100% Completed) Roof Slab: : 67 Sqm/67 Sqm (100% Completed)
Base Slab (At Roof Level): 0 Sqm/119 Sqm (0% Completed) Cover Slab: 0 Sqm/45Sqm (0% Completed)
Base Slab (At Roof Level): 20 Sqm/81 Sqm (25% Completed) Slab B/w RL and GL: 20 Sqm/98Sqm (20.4% Completed)
Base Slab: 138 Sqm/155 Sqm (89% Completed) Roof Slab: 98 Sqm/122Sqm (80% Completed)
Base Slab: 35 Sqm/35 Sqm (100% Completed) Roof Slab: 32 Sqm/32 Sqm (100% Completed)
Base Slab: 0 Sqm/44 Sqm (0% Completed) Roof Slab: 0 Sqm/27 Sqm (0% Completed)
Base Slab: 146 Sqm/146 Sqm (100% Completed) Roof Slab: 0 Sqm/124 Sqm (0% Completed)
Entrances
Base Slab: 180 Sqm/180 Sqm (100% Completed) Roof Slab: 0 Sqm/150 Sqm (0% Completed) Slab @ 2.4lvl: 0Sqm/279Sqm (0% Completed)
Base Slab: 176 Sqm/176 Sqm (100% Completed) Cover Slab: 0 Sqm/27 Sqm (0% Completed)
Base Slab: 57 Sqm/57 Sqm (100% Completed) Roof Slab: 0 Sqm/24 Sqm (0% Completed)
Base Slab: 121 Sqm/121 Sqm (100% Completed) Roof Slab: 41 Sqm/41 Sqm (0% Completed)
Base Slab:86 Sqm/86 Sqm (100% Completed) Plinth: 0 Sqm/18 Sqm (0% Completed)
|
3 | Cross Passages |
|
4 | Casting Yard at Wadala |
|
Sr. No. | Nature of Work | Status |
---|---|---|
1 | Tunneling & Segment Production Progress | TBM - 1 Tunneling completed (TBM dismantalling in progress) Temporary ring: Scope - 12 Completed CST - SKD: Scope - 476 Completed SKD - SGG: Scope - 499 Completed SGG - SGR: Scope - 1,110 Completed SGR - SMC: Scope - 635 Completed TBM - 2 Temporary ring: Scope - 12 Completed CST - SKD: Scope - 482 Completed SKD - SGG: Scope - 488 Completed SGG - SGR: Scope - 1,123 Completed SGR - SMC: Total progress - 422, Scope - 639 Note: TBM 2 stopped due to Parsi Fire Temple Issue on 20.07.2018 and resumed on 30.11.18 Second time stopped on 6.12.18 & resumed on 10.12.18 The productivity of TBM 2 is low due to unanticipated ground condition Segment Production Permanent Rings (including Upline & Downline) SCS - SKD: Scope - 961 Completed SKD - SGG: Scope - 713 Completed SGG - SGR: Scope - 1,913 Completed SGR - SMC: Scope - 991 Completed Temporary Rings (including Upline & Downline) SCS: Scope - 20 Completed SKD: Scope - 277 Completed SGG: Scope - 313 Completed SGR: Scope - 287 Completed |
2 | Excavation | CST Station Launching shaft: Scope - 25,859 Cum. Completed Station Box (with extended concourse) - Scope - 1,26,691 Cum. Completed Entry and Exit- Total Progress - 11,310 Cum. Scope - 29,956 Cum. Grant Road Station Box- Total Progress - 59,938 Cum. Scope - 1,03,536 Cum. EE-1(Phase-02) - Total Progress - 8,829, Scope - 9,329 EE-2(Phase-05) - Total Progress - 2,364, Scope - 2,959 EE-3 (Phase-08) - Scope - 2,686 Girgaon EE-2 (Swami Niwas) - Scope - 2,010 Station Box EE-3 (Extended conc.) - Total Progress - 24,036, Scope - 1,39,980 Kalbadevi Station Box- Total Progress K-1 Box - Total Progress - 2,307, Scope - 26,621 K-2 Box - Total Progress - 11,798, Scope - 52,000 |
3 | Base Slab Progress | CST Station Box: Total Progress - 180, Scope - 250 |
4 | Secant Piling Progress | CST Station Primary pile - Station Box: Scope - 359 Completed Secondary pile Station Box: Scope - 352 Completed Primary pile - Entry & Exit: Total progress - 620, Scope - 662 Secondary pile - Entry & Exit: Total progress - 628, Scope - 661 Grant Road Station Primary pile: Total progress - 370, Scope - 371 Secondary pile: Scope - 373 Completed Primary pile - Entry & Exit: Total progress - 53, Scope - 56 Secondary pile - Entry & Exit: Total progress - 48, Scope - 56 Girgaon Station Primary pile Station Box: Scope - 353 Completed Secondary pile Station Box: Total progress - 340, Scope - 345 Primary pile - Entry & Exit: Scope - 88 Completed Secondary pile - Entry & Exit: Scope - 88 Completed Kalbadevi Station K-2 Box Primary Pile Station Box: Scope - 167 Completed Secondary Pile Station Box: Scope - 167 Completed Kalbadevi Station K-1 Box Primary Pile Station Box: Scope - 96 Completed Secondary Pile Station Box: Scope - 96 Completed |
5 | Rehabilitation & Resettlement | Rehabilitation & Resettlement is in progress. Compensation meeting in progress with project affected residents in Kalbadevi and Girgaon. |
6 | Building condition Survey | Pre - Condition Survey Total Progress - 884 Scope - 1,004 Note: Additional 25M Topography survey on either of ZOI completed |
7 | Tree Cutting/transplantation | CST - Total Progress - 47 , Scope - 91 CST - Transplantation - Total Progress - 62 , Scope - 97 Grant Road - Total Progress - 28 , Scope - 28 Grant Road Transplantation - Total Progress - 21 , Scope - 21 Girgaon - Total Progress - 10 , Scope - 11 Girgaon Transplantation - Total Progress - 9 , Scope - 9 New Plantation at Aarey Colony - Total Progress - 205 , Scope - 35 |
8 | Traffic Diversion | Permission for Traffic Diversion at Girgaon station received and trial run road diversion started from 18th May 2017. Trail run for traffic diversion at Grant road done on 20th July’2017 and road diversion started from 27th July’2017. |
9 | Geo-technical investigation | Geo-technical investigation for Stations as well as Tunnel completed. |
10 | Barricading | Barricading for CST Station Box, Wadala Casting Yard and WTC completed. Barricading in Grant Road completed for Garden Side. Structural Steel barricading for Median done at Grant Road. Barricading in Girgaon completed for 619 RM out of 619 RM (Approx.) Barricading in Kalbadevi station started as per land available on 29.09.18 |