1 | Tunneling & Segment Production Progress | CSIA T2 Metro Station |
Tunnel CSIA T2 to Sahar Road Station (Downline): |
Permanat Ring: Total Progress - 491, Scope - 491 |
Completed |
Permanat Ring: Total Progress - 491, Scope - 491 |
Completed |
Tunnel MVS to CSIA T1 (Upline): |
Permanat Ring: Total Progress - 910, Scope - 910 |
Completed |
Tunnel MVS to CSIA T1 (Downline): |
Permanat Ring: Total Progress - 892, Scope - 892 |
Completed |
Sahar Road Station to CSMIA |
Domestic Airport Station (Downline) |
Permanat Ring: Total Progress - 1080, Scope - 1080 |
Segment Production Progress: |
Permanent Rings: Total progress - 4949, Scope - 4949 |
2 | Excavation | CSIA T1 Metro station |
Total progress - 268971 Cum. Scope - 268471 Cum. (Work in progress) |
Sahar road Station |
Total progress - 322478 Cum. Scope - 322478 Cum. (Completed) |
CSIA T2 Metro Station |
Total progress - 468642 Cum. Scope - 468642 Cum. (Completed) |
3 | Base Slab Progress | CSIA T1 Metro station: |
Base Slab Completed. |
Concourse Slab: Total progress - 196 m. Scope - 198 m. (Work in progress) |
Concourse to Roof Slab: Total progress - 370 m. Scope - 390 m. (Work in progress) |
Roof Slab: Total progress - 196 m. Scope - 198 m. (Work in progress) |
CSIA T2 Metro Station: |
Base Slab Completed. |
Concourse Slab: Total progress - 311 m. Scope - 314 m. (Work in progress) |
Concourse to Roof Wall: Total progress - 499 m. Scope - 541 m. (Work in progress) |
Roof Slab: Total progress - 311 Cum. Scope - 314 m. (Work in progress) |
Sahar Road Metro station: |
Base Slab Completed. |
Concourse Slab: Total progress - 220 m. Scope - 220 m. (Completed) |
Concourse to Roof Slab: Total progress - 328 m. Scope - 328 m. (Completed) |
Roof Slab: Total progress - 220 Cum. Scope - 220 m. (Completed) |
4 | Secant Piling Progress | CSIA T1 Metro station |
Secant piles: Total progress - 808, Scope - 808 |
Micro piles: Total progress - 154, Scope - 154 |
Sahar road Station |
Secant piles: Total progress - 1121, Scope - 1121 |
Subway secant piles: Total progress - 67, Scope - 67 |
CSIA T2 Metro Station |
Secant piles: Total progress - 1298, Scope - 1298 |
5 | Rehabilitation & Resettlement | ______ |
6 | Building condition Survey | Pre-condition survey this week - 0 |
Total Progress - 60 |
Scope - 60 |
7 | Tree Cutting/transplantation | CSIA T1 - Total progress - 3 , Scope - 3 , Completed |
Transplantation - 60 out of 112 |
Sahar Rorad - Total progress - 4 , Scope - 4 , Completed |
Transplantation - 177 out of 226 |
CSIA T2 - Total progress - 0 , Scope - 0 , Completed |
Transplantation - 4 out of 4 completed |
8 | Traffic Diversion | SAHAR ROAD STATION: |
Road diversion: Stage-1 Completed |
Subway completed |
Sahar Shadow Road: |
Commissioned on 27th July 2018. |
Caping beam & Flood Wall: Completed |
CSIA T2 Metro Station: |
Internal Road: Completed. |
Ancillary Works for TBM Launching: Completed |
9 | Geo-technical investigation | SAHAR Road Metro station |
Completed |
Sahar Road to International Station |
CSIA T1 Metro Station |
Completed |
CSIA T2 Metro Station |
Completed |
10 | Barricading | SAHAR Road Metro station |
All construction Works is going on within |
secured barricading area . |
CSIA T1 Metro station |
Completed |
CSIA T2 Metro station |
Completed |
Construction Depot JVLR (GI Sheets) |
Completed |