1. ITO Junction-BKC | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | Scope(No.) | This Week | Total Progress | %Completion | Remarks | ||||||
Decking Plate Erection-Phase 1 | 550 | - | 550 | 100% | Completed | ||||||
Decking Plate Erection-Phase 1 | 550 | - | 550 | 100% | Completed |
2. Utility Diversion | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
2.1. Dharavi | |||||||||||
Utility Type | Total Scope (Rmt) | This Week | Total Progress | % Completion | Remarks | ||||||
450 mm Dia Water Line (Building side) | 332 | - | 332 | 100% | Completed | ||||||
SWD - 2200 X 2200 East | 155 | - | 155 | 100% | Completed | ||||||
900 mm Dia Water Line | 300 | - | 300 | 100% | Completed | ||||||
1200 mm SWD Building site | 300 | - | 300 | 100% | Completed | ||||||
5.2. BKC | |||||||||||
900 mm Dia SWD – TATA Footpath | 165 | - | 165 | 100% | Completed | ||||||
600 mm Dia SWD – IT Junction | 210 | - | 210 | 100% | Completed | ||||||
SWD Line- 2m X 2m | 48 | - | 48 | 100% | Completed | ||||||
450mm Dia SWD- N. Shaft | 165 | - | 165 | 100% | Completed | ||||||
5.3. Vidyanagari | |||||||||||
300 mm Dia Sewer Line (N. Shaft) | 325 | - | 325 | 100% | Completed | ||||||
SWD & Culvert | 205 | - | 205 | 100% | Completed | ||||||
600 mm Dia Pipeline(Phase 1) | 232 | - | 232 | 100% | Completed | ||||||
1200 mm Dia Pipeline | 245 | - | 245 | 100% | Completed | ||||||
5.4. Santacruz | |||||||||||
600 mm Dia Sewer Line | 150 | - | 150 | 100% | Completed | ||||||
SWD Below flyover | 360 | - | 360 | 100% | Completed | ||||||
300mm Dia Sewer line | 280 | - | 280 | 100% | Completed | ||||||
5.5. MVS | |||||||||||
1200 mm Water Line Diversion | 45 | - | 45 | 100% | Completed |
3. PILING | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
3.1. Dharavi | |||||||||||
Location | Total Scope (Nos) | This Week | Total Progress | % Completion | Remarks | ||||||
North Retrieval & Ancillary | 307 | - | 307 | 100% | Completed | ||||||
Station Box | 779 | - | 779 | 100% | Completed | ||||||
Decking Piles-King Post (Interconnection) | 52 | - | 52 | 100% | Completed | ||||||
3.2. BKC | |||||||||||
Location | Total Scope (Nos) | This Week | Total Progress | % Completion | Remarks | ||||||
North Launching shaft | 180 | - | 180 | 100% | Completed | ||||||
Station Box | 1155 | - | 1155 | 100% | Completed | ||||||
South Launching | 185 | - | 185 | 100% | Completed | ||||||
Decking Piles | 6 | - | 6 | 100% | Completed | ||||||
Entry/Exit-15-19-East(E10) | 76 | - | 76 | 100% | Completed | ||||||
Entry/Exit-15-19-East(E11) | 121 | - | 121 | 100% | Completed | ||||||
Entry/Exit-15-19-East(E05) | 292 | - | 229 | 74% | Ongoing | ||||||
Entry/Exit-15-19-East(E02) | 176 | - | 176 | 100% | Completed | ||||||
Entry/Exit-38-40-East(E07) | 220 | - | 162 | 13% | Ongoing | ||||||
Entry/Exit-11-13-East(E04) | 93 | 6 | 26 | 28% | Ongoing | ||||||
3.3. Vidyanagri | |||||||||||
Location | Total Scope (Nos) | This Week | Total Progress | % Completion | Remarks | ||||||
North Launching shaft | 176 | - | 176 | 100% | Completed | ||||||
Station Box | 894 | - | 894 | 100% | Completed | ||||||
3.4. Santacruz | |||||||||||
Location | Total Scope (Nos) | This Week | Total Progress | % Completion | Remarks | ||||||
Secant pile | 585 | - | 585 | 100% | Completed | ||||||
Micro pile(station box) | 2182 | - | 2182 | 100% | Completed | ||||||
Secant pile-(ent/ext)-South Entry Exit | 163 | - | 163 | 100% | Completed | ||||||
Secant pile-(ent/ext)-North Entry Exit | 112 | - | 112 | 100% | Completed | ||||||
Entry - Exit (Micro Piles) Gr 07 (South West Entry Exit) | 465 | - | 465 | 100% | Completed | ||||||
Entry - Exit (Micro Piles) Gr 17 (North West Entry Exit) | 469 | - | 469 | 100% | Completed | ||||||
Entry - Exit (Secant Piles) Gr 07 (SW Entry Exit) | 252 | - | 252 | 100% | Completed | ||||||
Entry - Exit (Micro Piles) Gr 17 (N-W Entry Exit) | 333 | - | 333 | 100% | Completed | ||||||
3.5. MVS | |||||||||||
Secant Pile | 184 | - | 184 | 100% | Completed |
4. Capping Beam | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
4.1. Dharavi | |||||||||||
Location | Total Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Station Box | 717 | - | 717 | 100% | Completed | ||||||
4.2. BKC | |||||||||||
North Launching Shaft | 133 | - | 133 | 100% | Completed | ||||||
Station Box | 860 | - | 860 | 100% | Completed | ||||||
South Launching Shaft | 109 | - | 109 | 100% | Completed | ||||||
4.3. Vidyanagri | |||||||||||
North Shaft | 110 | - | 110 | 100% | Completed | ||||||
Station Box | 680 | - | 680 | 100% | Completed | ||||||
4.4. Santacruz & MVS | |||||||||||
Station Box-Santacruz | 560 | - | 560 | 100% | Completed | ||||||
North E&E-Santacruz | 60 | - | 60 | 100% | Completed | ||||||
Station Box-MVS | 110 | - | 110 | 100% | Completed |
5. Excavation | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Station Box (Dharavi) | 179000 | - | 1,79,000 | 100% | Completed | ||||||
Station Box (BKC) | 377624 | - | 3,77,624 | 100% | Completed | ||||||
Station Box (Vidyanagri) | 161118 | - | 1,61,118 | 100% | Completed | ||||||
Santacruz (Station box) | 104500 | - | 1,04,500 | 100% | Completed | ||||||
Entry Exit (BKC)(EE02) | 4736 | - | 3290 | 68% | Ongoing | ||||||
Entry Exit-SSC (NWEE &SWEE) | 23578 | 110 | 19700 | 83% | Ongoing |
6. Permanent Works-Dharavi | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | UOM | Scope | This Week | Total Progress | % Comp | Remarks | |||||
Base Slab | Rmt | 250 M | - | 250 M | 100% | Completed | |||||
Concourse Slab | Rmt | 250 M | - | 250 M | 100% | Completed | |||||
Roof Slab | Rmt | 250 M | - | 250 M | 100% | Completed | |||||
Platform Slab | Rmt | 250 M | - | 250 M | 100% | Completed | |||||
Pop up Walls | Rmt | 790 M | 507 M | 57.5% | Ongoing | ||||||
Pop up Slab | Nos | 10 | 6 | 35% | Ongoing | ||||||
EE Slabs | Nos | 8 | 6 | 63% | Ongoing | ||||||
Ancillary Slabs | Nos | 6 | 5.5 | 64% | Ongoing | ||||||
Backfilling | Cum | 38961 | 22521 | 57% | Ongoing | ||||||
Blockwork | Cum | 1337 | 11 | 1021 | 76% | Ongoing |
7. Permanent Works-BKC | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | UOM | Scope | This Week | Total Progress | % Comp | Remarks | |||||
Base Slab | Rmt | 474 M | - | 474 M | 100% | Completed | |||||
Concourse Slab | Rmt | 474 M | - | 463 MM | 95% | Ongoing | |||||
Roof Slab | Rmt | 474 M | - | 445 M | 94% | Ongoing | |||||
Platform Slab | Rmt | 674 M | - | 655 M | 97% | Ongoing | |||||
Pop up Walls | Rmt | 782 M | 439 M | 56% | Ongoing | ||||||
Pop up Slab | Nos | 11 | 4 | 36% | Ongoing | ||||||
EE Slabs | Nos | 32 | 3.5 | 63% | Ongoing | ||||||
Ancillary Slabs | Nos | 4 | 2 | 50% | Ongoing | ||||||
Backfilling | Cum | 97,135 | 26,100 | 26% | Ongoing | ||||||
Blockwork | Cum | 2,458 | 12 | 2,265 | 86% | Ongoing |
8. Permanent Works-Vidyanagari | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | UOM | Scope | This Week | Total Progress | % Comp | Remarks | |||||
Base Slab | Rmt | 250 M | 6 | 242 M | 98% | Ongoing | |||||
Concourse Slab | Rmt | 250 M | 238 M | 95% | Ongoing | ||||||
Roof Slab | Rmt | 250 M | 232 M | 93% | Ongoing | ||||||
Platform Slab | Rmt | 250 M | 227 M | 91% | Ongoing | ||||||
Pop up Walls | Rmt | 544 M | 507M | 84% | Ongoing | ||||||
Pop up Slab | Nos | 8 | 7 | 87% | Ongoing | ||||||
EE Slabs | Nos | 4 | 4 | 100% | Completed | ||||||
Ancillary Slabs | Nos | 6 | 5 | 91% | Ongoing | ||||||
Backfilling | Cum | 39848 | 18643 | 44% | Ongoing | ||||||
Blockwork | Cum | 1676 | 4 | 1095 | 64% | Ongoing |
9. Permanent Works-Santacruz | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Location | UOM | Scope | This Week | Total Progress | % Comp | Remarks | |||||
Base Slab | Rmt | 252 M | 252 M | 100% | Completed | ||||||
Concourse Slab | Rmt | 252 M | 252 M | 100% | Ongoing | ||||||
Roof Slab | Rmt | 252 M | - | 252 M | 100% | Ongoing | |||||
Platform Slab | Rmt | 252 M | - | 242 M | 96% | Ongoing | |||||
Plant Room Base Slab | Rmt | 91 M | 91 | 100% | Completed | ||||||
Pop up Walls | Rmt | 773 M | 533M | 72% | Ongoing | ||||||
Pop up Slab | Nos | 9 | 6 | 66% | Ongoing | ||||||
Shafts | Nos | 9 | 3 | 22% | Ongoing | ||||||
Backfilling | Cum | 27928 | 10464 | 37% | Ongoing | ||||||
Blockwork | Cum | 1589 | 5 | 901 | 64% | Ongoing |
10. NATM: BKC South | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Excavation-Heading | 153 | - | 153 | 100% | Completed | ||||||
Excavation-Benching | 153 | - | 153 | 100% | Completed | ||||||
Concreting-Invert | 153 | - | 153 | 100% | Completed | ||||||
Concreting-Overt | 153 | - | 153 | 100% | Completed | ||||||
Concreting-Invert | 8.3 | - | Ongoing | ||||||||
Concreting-Overt | 8.3 | - |
11. NATM: BKC North | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Excavation-Heading | 153 | 153 | 100% | Completed | |||||||
Excavation-Benching | 153 | 153 | 100% | Completed | |||||||
Concreting-Invert | 153 | - | 153 | 100% | Completed | ||||||
Concreting-Overt | 153 | - | 153 | 100% | Completed |
12. NATM: SANTACRUZ (PLATFORM TUNNEL) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Excavation-Heading | 272 | 272 | 100% | Completed | |||||||
Excavation-Benching | 272 | 272 | 100% | Completed | |||||||
Concreting-Invert | 272 | - | 272 | 100% | Completed | ||||||
Concreting-Overt | 272 | - | 272 | 100% | Completed |
13. NATM: CROSS PASSAGES – (SBA to MVS) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
CP – 507 | 1 | - | 1 | 100% | Completed | ||||||
CP – 508 | 1 | - | 1 | 100% | Completed | ||||||
CP – 509 | 1 | - | 1 | 100% | Completed | ||||||
CP – 510 | 1 | - | 1 | 100% | Completed | ||||||
CP – 511 | 1 | - | 1 | 100% | Completed | ||||||
CP – 512 | 1 | - | 1 | 100% | Completed | ||||||
NATM CP-01 | 1 | - | 1 | 100% | Completed | ||||||
NATM CP-02 | 1 | - | 1 | 100% | Completed | ||||||
NATM CP-03 | 1 | - | 1 | 100% | Completed |
14. NATM: CROSS PASSAGES – (SBA to SDH) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
CP – 501 | 1 | 1 | 100% | Completed | |||||||
CP – 502 | 1 | 1 | 100% | Completed | |||||||
CP – 503 | 1 | 1 | 100% | Completed | |||||||
CP – 504 | 1 | 1 | 100% | Completed | |||||||
CP – 505 | 1 | 1 | 100% | Completed | |||||||
CP – 506 | 1 | 1 | 100% | Completed |
15. NATM: CP – (SSC) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
A1 | 1 | 1 | 100% | Completed | |||||||
B1 | 1 | 1 | 100% | Completed | |||||||
C1 | 1 | 1 | 100% | Completed | |||||||
A2 | 1 | 1 | 100% | Completed | |||||||
B2 | 1 | 1 | 100% | Completed | |||||||
C2 | 1 | 1 | 100% | Completed | |||||||
A4 | 1 | 1 | 100% | Completed | |||||||
A5 | 1 | 1 | 100% | Completed | |||||||
A6 | 1 | 1 | 100% | Completed |
16. NATM: SANTACRUZ (Ventilation Tunnel) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Activity | Scope | This Week | Total Progress | % Completion | Remarks | ||||||
Excavation-Heading | 23 | 23 | 100% | Completed | |||||||
Excavation-Benching | 23 | 23 | 100% | Completed | |||||||
Concreting-Invert | 23 | - | 23 | 100% | Completed | ||||||
Concreting-Overt | 23 | - | 23 | 100% | Completed |