Sr. No. | Nature of Work | Project Status |
1 | Tunneling Works |
|
2 | Station Works |
Entrances
Base Slab: 553 Sqm/553 Sqm (100% Completed) Intermediate Slab: 628 Sqm/628 Sqm (100% Completed) Roof Slab: 740 Sqm/740 Sqm (100% Completed)
Base Slab: 639 Sqm/639 Sqm (100% Completed) Intermediate Slab: 662 Sqm/662 Sqm (100% Completed) Roof Slab: 399 Sqm/399 Sqm (100% Completed)
Base Slab: 375 Sqm/375 Sqm (100% Completed) Intermediate Slab: 238 Sqm/238 Sqm (100% Completed) Roof Slab: 175 Sqm/175 Sqm (100% Completed)
Base Slab: 272 Sqm/272 Sqm (100% Completed) Roof Slab: 206Sqm/206 Sqm (100% Completed)
Base Slab: 143 Sqm/143 Sqm (100% Completed) Roof Slab: 212 Sqm/212 Sqm (100% Completed)
Base Slab: 65 Sqm/86.4 Sqm (75% Completed) Roof Slab:61Sqm/61 Sqm (100% Completed)
Entrances
Base Slab: 80 Sqm/80 Sqm (100% Completed) Roof Slab: : 67 Sqm/67 Sqm (100% Completed)
Base Slab (At Roof Level): 0 Sqm/119 Sqm (0% Completed) Cover Slab: 0 Sqm/45Sqm (0% Completed)
Base Slab (At Roof Level): 20 Sqm/81 Sqm (25% Completed) Slab B/w RL and GL: 20 Sqm/98Sqm (20.4% Completed)
Base Slab: 138 Sqm/155 Sqm (89% Completed) Roof Slab: 98 Sqm/122Sqm (80% Completed)
Base Slab: 35 Sqm/35 Sqm (100% Completed) Roof Slab: 32 Sqm/32 Sqm (100% Completed)
Base Slab: 0 Sqm/44 Sqm (0% Completed) Roof Slab: 0 Sqm/27 Sqm (0% Completed)
Base Slab: 146 Sqm/146 Sqm (100% Completed) Roof Slab: 0 Sqm/124 Sqm (0% Completed)
Entrances
Base Slab: 180 Sqm/180 Sqm (100% Completed) Roof Slab: 0 Sqm/150 Sqm (0% Completed) Slab @ 2.4lvl: 0Sqm/279Sqm (0% Completed)
Base Slab: 176 Sqm/176 Sqm (100% Completed) Cover Slab: 0 Sqm/27 Sqm (0% Completed)
Base Slab: 57 Sqm/57 Sqm (100% Completed) Roof Slab: 0 Sqm/24 Sqm (0% Completed)
Base Slab: 121 Sqm/121 Sqm (100% Completed) Roof Slab: 41 Sqm/41 Sqm (0% Completed)
Base Slab:86 Sqm/86 Sqm (100% Completed) Plinth: 0 Sqm/18 Sqm (0% Completed)
|
3 | Cross Passages |
|
4 | Casting Yard at Wadala |
|