Sr. No. | Nature of Work | Status |
---|---|---|
1 | Tunneling & Segment Production Progress | TBM - 1 Tunneling completed (TBM dismantalling in progress) Temporary ring: Scope - 12 Completed CST - SKD: Scope - 476 Completed SKD - SGG: Scope - 499 Completed SGG - SGR: Scope - 1,110 Completed SGR - SMC: Scope - 635 Completed TBM - 2 Temporary ring: Scope - 12 Completed CST - SKD: Scope - 482 Completed SKD - SGG: Scope - 488 Completed SGG - SGR: Scope - 1,123 Completed SGR - SMC: Total progress - 422, Scope - 639 Note: TBM 2 stopped due to Parsi Fire Temple Issue on 20.07.2018 and resumed on 30.11.18 Second time stopped on 6.12.18 & resumed on 10.12.18 The productivity of TBM 2 is low due to unanticipated ground condition Segment Production Permanent Rings (including Upline & Downline) SCS - SKD: Scope - 961 Completed SKD - SGG: Scope - 713 Completed SGG - SGR: Scope - 1,913 Completed SGR - SMC: Scope - 991 Completed Temporary Rings (including Upline & Downline) SCS: Scope - 20 Completed SKD: Scope - 277 Completed SGG: Scope - 313 Completed SGR: Scope - 287 Completed |
2 | Excavation | CST Station Launching shaft: Scope - 25,859 Cum. Completed Station Box (with extended concourse) - Scope - 1,26,691 Cum. Completed Entry and Exit- Total Progress - 11,310 Cum. Scope - 29,956 Cum. Grant Road Station Box- Total Progress - 59,938 Cum. Scope - 1,03,536 Cum. EE-1(Phase-02) - Total Progress - 8,829, Scope - 9,329 EE-2(Phase-05) - Total Progress - 2,364, Scope - 2,959 EE-3 (Phase-08) - Scope - 2,686 Girgaon EE-2 (Swami Niwas) - Scope - 2,010 Station Box EE-3 (Extended conc.) - Total Progress - 24,036, Scope - 1,39,980 Kalbadevi Station Box- Total Progress K-1 Box - Total Progress - 2,307, Scope - 26,621 K-2 Box - Total Progress - 11,798, Scope - 52,000 |
3 | Base Slab Progress | CST Station Box: Total Progress - 180, Scope - 250 |
4 | Secant Piling Progress | CST Station Primary pile - Station Box: Scope - 359 Completed Secondary pile Station Box: Scope - 352 Completed Primary pile - Entry & Exit: Total progress - 620, Scope - 662 Secondary pile - Entry & Exit: Total progress - 628, Scope - 661 Grant Road Station Primary pile: Total progress - 370, Scope - 371 Secondary pile: Scope - 373 Completed Primary pile - Entry & Exit: Total progress - 53, Scope - 56 Secondary pile - Entry & Exit: Total progress - 48, Scope - 56 Girgaon Station Primary pile Station Box: Scope - 353 Completed Secondary pile Station Box: Total progress - 340, Scope - 345 Primary pile - Entry & Exit: Scope - 88 Completed Secondary pile - Entry & Exit: Scope - 88 Completed Kalbadevi Station K-2 Box Primary Pile Station Box: Scope - 167 Completed Secondary Pile Station Box: Scope - 167 Completed Kalbadevi Station K-1 Box Primary Pile Station Box: Scope - 96 Completed Secondary Pile Station Box: Scope - 96 Completed |
5 | Rehabilitation & Resettlement | Rehabilitation & Resettlement is in progress. Compensation meeting in progress with project affected residents in Kalbadevi and Girgaon. |
6 | Building condition Survey | Pre - Condition Survey Total Progress - 884 Scope - 1,004 Note: Additional 25M Topography survey on either of ZOI completed |
7 | Tree Cutting/transplantation | CST - Total Progress - 47 , Scope - 91 CST - Transplantation - Total Progress - 62 , Scope - 97 Grant Road - Total Progress - 28 , Scope - 28 Grant Road Transplantation - Total Progress - 21 , Scope - 21 Girgaon - Total Progress - 10 , Scope - 11 Girgaon Transplantation - Total Progress - 9 , Scope - 9 New Plantation at Aarey Colony - Total Progress - 205 , Scope - 35 |
8 | Traffic Diversion | Permission for Traffic Diversion at Girgaon station received and trial run road diversion started from 18th May 2017. Trail run for traffic diversion at Grant road done on 20th July’2017 and road diversion started from 27th July’2017. |
9 | Geo-technical investigation | Geo-technical investigation for Stations as well as Tunnel completed. |
10 | Barricading | Barricading for CST Station Box, Wadala Casting Yard and WTC completed. Barricading in Grant Road completed for Garden Side. Structural Steel barricading for Median done at Grant Road. Barricading in Girgaon completed for 619 RM out of 619 RM (Approx.) Barricading in Kalbadevi station started as per land available on 29.09.18 |