Sr. No | Nature of Work | Status |
---|---|---|
1 | Barricading | Handed over areas barricaded |
2 | Rehabilitation & Resettlement | Vidhan Bhavan Station: Alternate eatery (Kutumbsakhi) has been occupied at new location. Hutatma Chowk: Container placed at alternate location for Police Chowky. Electricity & water connection and signing of MoU awaited for shifting. |
3 | Traffic Diversion & Decking | Phase-1 Traffic Diversions implemented at all station locations Cuffe Parade- Deck at service lane open to traffic Vidhan Bhavan- Both decks at Free Press Journal Road open to traffic Churchgate- Straight Deck and cross deck open to traffic. Hutatma Chowk- Straight Deck open to traffic Mid Shaft- Approval Awaited |
4 | Geo-technical investigation | Completed for all stations and alignment |
5 | Tree Cutting/transplantation | Cuffe Parade Station - Scope: (To be transplanted/to be cut)= 123 / 196 Completed: ( transplanted/ cut ) = 120 / 190 Vidhan Bhavan Station - Scope: (To be transplanted/to be cut)= 94 / 116 Completed: ( transplanted/ cut ) = 67/92 (All cutting/ transplantation completed as 23 trees are being saved) Church Gate Station Scope: (To be transplanted/to be cut)= 47 /51 Completed: ( transplanted/ cut ) = 40 / 38 (All cutting/ transplantation completed as 51 trees are being saved) Hutatma Chowk Station Scope: (To be transplanted/to be cut)= 76 / 45 Completed: ( transplanted/ cut ) = 44 / 43 (All cutting/ transplantation completed as 35 are being saved) Mid Shaft Scope: (To be transplanted/to be cut)= 03 / 05 Completed: ( Transplanted/ cut ) = 02/ 03 |
6 | Building condition Survey | 100% completed |
7 | Tunneling Progress | TBM Ring Building(rmtr): TBM1: Total completed: 2,926.5 Scope: 2,926.5(4 Breakthrough Over) TBM2: Total completed: 2,939.3 Scope: 2,939.3 (4 Breakthrough Over) First Stage Concrete: TBM1: Total completed:2,910.4 Scope: 2,910.4(Started on 06/01/21 in SCP to SVB Upline, started on 05/02/21 in SVB to SCG Upline, started on 19/08/21 in SCG to SHC Upline, Started on 06/11/21 in SHC to CST Upline)
TBM2: Total completed: 2,919 Scope: 2939.3 (Started on 02/12/20 at SVB to SCG Downline; Started on 27/03/21 in SCP to SVB Downline, Started on 30/07/21 in SCG to SHC Downline)
NATM 1: Total completed: 199.12 Scope: 199.12 (Started on 03/04/21 at SCP NATM 1 Upline) NATM 2: Total completed: 200.2 Scope: 200.2 (Started on 30/04/21 at SCP NATM 2 Downline) |
8 | Segment Production Progress | 100% Complete (4,166 nos) |
9 | Secant Piling Progress | Cuffe Parade Station - Total completed -1,371; Scope –1,371(Only Station Box); Entry Exit: 347 out of 347 completed; Vent Shaft: 26 out of 26 completed. Vidhan Bhavan Station - Total completed -1,897; Scope – 1,897 (Station Box Piling completed); Church Gate Station - Total completed -1,406; Scope – 1,406 Hutatma Chowk Station - Total completed – 1,796; Scope – 1,796; Utility Gallery: 97 out of 160 completed. Mid Shaft - Total completed – 172; Scope – 172 (Secant Piles) Total completed – 50; Scope – 50 (ISMB Soldier Piles) |
10 | Excavation | Cuffe Parade Station: 305265 cum. out of 3,06,750 cum. Vidhan Bhavan Station: 217189.01 cum. out of 2,17,474 cum.
Churchgate Station: 207831.37 cum. out of 2,13,592 cum.
Hutatma Chowk Station: 178271.84 cum. out of 1,81,998 cum.
Mid Shaft: 13,724 cum. out of 13,724 cum. |
11 | Permanent Works | Permanent Base Slab:
Concourse Slab:
Mezzanine/ Other Slab:
Roof Slab:
Platform Slab:
|
12 | NATM Tunnel (Heading) | Upline: Total Completed: 199.12m Scope: 199.12m Downline: Total Completed: 200.20m Scope: 200.20m SHC NATM PF: Total Completed: 257.50m Scope: 257.5m |
13 | NATM Tunnel (Benching) | Upline: Total Completed: 199.12m Scope: 199.12m Downline: Total Completed: 200.20m Scope: 200.20m SHC NATM PF: Total Completed: 257.5m Scope: 257.5m |
14 | NATM Tunnel (Secondary Lining) | Upline Invert: 199.12m completed out of 199.12m Upline Overt: 199.12m completed out of 199.12m Downline Invert: 200.0m completed out of 200.20m Downline Overt: 200.2m completed out of 200.20m SHC NATM PF Invert: Total Completed: 258m Scope: 257.50m SHC NATM PF Overt: Total Completed: 73m Scope: 257.50m |