Sr. No | Nature of Work | Status |
---|---|---|
1 | Barricading | 100 % completed. In progress with the construction works. |
2 | Rehabilitation & Resettlement | Completed. |
3 | Traffic Diversion | Completed. |
4 | Geo-technical investigation | 100% completed. |
5 | Building condition Survey | Completed. |
6 | Tunneling Progress | Science Museum- Worli (Tansa-1) – 1382/ 1382 rings has been erected. (100 % completed) Science Museum- Worli (Tansa-2) – 1372 / 1372 rings has been erected. (100 % completed)
Science Museum-Mumbai Central (Tansa-2) – 1182 / 1308 rings has been erected. (90.36 % Completed) Science Museum-Mumbai Central (Tansa-1) – 792 / 1303 rings has been erected. (60.78 % Completed) |
7 | Segment Production Progress | 100 % of the total scope of permanent rings has been completed. |
8 | Secant Piling Progress | Station Box Area:
Mumbai Central – 100 % completed Mahalaxmi – 100 % completed Science Museum – 100 % completed Acharya Atre Chowk –100 % completed Worli – 100 % completed |
9 | Traffic Decking & King Posts |
Mumbai Central –100 % has been completed. Mahalaxmi – 100 % has been completed. Acharya Atre Chowk- 100 % has been completed. Worli – 100 % has been completed.
|
10 | Excavation (Station Box) | Mumbai Central: 2,14,164 / 2,14,164 cu.m ( 100% ) has been completed.
Mahalaxmi: 1,66,229 / 1,66,229 cu.m ( 100%) has been completed.
Science Museum : 2,11,816 / 2,11,816 cu.m ( 100 %) has been completed.
Acharya Atre Chowk: 1,87,375 / 1,87,375 cu.m ( 100 % ) has been completed.
Worli: 1,77,370 / 1,77,370 cu.m ( 100% ) has been completed.
|
11 | Base Slab Progress | Mumbai Central: 100 % of the total scope has been completed.
Mahalaxmi: 100% of the total scope has been completed.
Science museum: 100 % of the total scope has been completed.
Acharya Atre Chowk: 100 % of the total scope has been completed.
Worli: 100 % of the total scope has been completed.
|
12 | Concourse Slab Progress | Mumbai Central: 100 % of the total scope has been completed.
Mahalaxmi: 100 % of the total scope has been completed.
Science museum: 100 % of the total scope has been completed.
Acharya Atre Chowk: 87 % of the total scope has been completed.
Worli: 98 % of the total scope has been completed.
|
13 | Roof Slab Progress |
Mumbai Central: 100 % of the total scope has been completed.
Mahalaxmi: 100 % of the total scope has been completed.
Science museum: 100 % of the total scope has been completed.
Acharya Atre Chowk: 58 % of the total scope has been completed.
Worli: 97 % of the total scope has been completed.
|
14 | Platform Slab Progress | Mumbai Central: 68 % of the total scope has been completed.
Mahalaxmi: 20 % of the total scope has been completed.
Science museum: 69 % of the total scope has been completed.
Acharya Atre Chowk: 39 % of the total scope has been completed.
Worli: 57 % of the total scope has been completed.
|